Safety Guide

Electrical SWMS

What to address when preparing a safe work method statement for electrical work, including energised installations, isolation, and operator competency.

Last reviewed October 2026

When electrical work is high risk construction work

Work on or near energised electrical installations or services is high risk construction work under the model WHS Regulations and requires a SWMS. The trigger applies to work on or near energised installations and services, regardless of voltage.

Electrical work also carries hazards that require documented risk controls even outside the high risk construction work definition. A SWMS for electrical work should identify the specific tasks, the installations involved, the isolation points, and the controls for shock, arc flash, and test instruments.

Key electrical hazards

Electric shock is the most recognised hazard, but arc flash can cause serious burns and other injuries even without direct contact. Other hazards include incorrect test instrument selection, working on circuits that are not isolated, and residual voltage in capacitors or cables after disconnection.

The SWMS should address how the work is planned, how the installation is identified, and how the presence or absence of voltage is verified. It should also cover the use of insulated tools, protective equipment, and the role of a second person for certain tasks.

Isolation and lockout-tagout

Where it is reasonably practicable, electrical work should be done de-energised. The installation should be isolated, locked out, and tagged, and then tested for dead before work begins. The SWMS should describe the isolation points, the lockout-tagout process, and how the absence of voltage is confirmed.

Energised work should only be carried out where it is not reasonably practicable to isolate, and only by competent persons with appropriate controls. The SWMS should set out the justification for energised work, the controls in place, and the competencies required.

Competency and planning

Electrical work generally requires an electrical licence, and the SWMS should list the licences and competencies needed for the work. The document should cover how the installation is identified, how isolation is verified, and how insulated tools and PPE are selected for the task.

Templates provide a useful starting point, but the installation, environment, and scope vary. The PCBU must review and adapt the SWMS for the specific electrical work before it is used.

Electrical Documents

Preparation Checklist

  • Identify the installation and the specific tasks to be carried out
  • Identify all isolation points and confirm they are accessible
  • Isolate, lock out, and tag the installation, then test for dead to verify the absence of voltage
  • Confirm the electrical licence and competencies required for the work
  • Select insulated tools and PPE suited to the task and any arc flash risk
  • Justify and document any energised work where isolation is not reasonably practicable
  • Arrange a second person for tasks that require it
  • Plan emergency response, including first aid for electric shock and arc flash

Frequently Asked Questions

When does electrical work require a SWMS?

Work on or near energised electrical installations or services is high risk construction work under the model WHS Regulations and requires a SWMS. Other electrical work still needs documented risk controls.

Should electrical work always be done de-energised?

Where it is reasonably practicable, electrical work should be done de-energised, with the installation isolated, locked out, tagged, and tested for dead. Energised work should only be carried out where isolation is not reasonably practicable, with appropriate controls and competent persons.

What is arc flash and why does it matter?

Arc flash is a release of energy caused by an electrical fault that can cause serious burns and other injuries without direct contact. The SWMS should address arc flash risk through isolation, protective equipment, and work methods that limit exposure.

Related Guides

References & Further Reading

This guide provides general information about WHS requirements in Australia. It is not legal advice. Safe work method statements available from Cornerstone SWMS are professional templates that must be reviewed and adapted by the PCBU for the specific worksite before use.

Browse All Documents
Cornerstone SWMS

Professional SWMS and SOP documents for Australian workplaces. Professionally drafted, editable, and instantly downloadable.

Legislation & Standards

  • Work Health and Safety Act 2011 (Cwlth)
  • State & Territory WHS Legislation
  • Safe Work Australia Guidelines

Disclaimer: All documents provided on this platform are templates and starting points only. They must be reviewed, adapted, and approved by the Person Conducting a Business or Undertaking (PCBU) or facilitated by a designated WHS Manager, Site Supervisor, or Principal Contractor, before use at any specific worksite. Site-specific hazards, conditions, and legislative requirements may vary. Cornerstone SWMS accepts no liability for documents used without appropriate review and customisation.